Install gas regulators
Complete these steps to install gas regulators for the plasma cutting system.
-
Install the gas regulators before the supply gas plumbing.
For installation steps, refer to the instruction manual for the gas regulator.
- Put a gas regulator 3 meters (10 feet) or less from the gas connect console, or adjust inlet gas pressures to be in the tolerances specified in Process-gas requirements for all gas connect consoles.
-
After installation, fully pressurize the system, and look for gas leaks.
Your system installer or a licensed plumber can do this for you.
-
Make sure that all gas fittings are tightened to the correct torque
specifications.
Refer to Supply gas installation.