Maintenance log for XPR cutting systems

You can make copies of this maintenance log to monitor tasks.

Table 1. Tasks for one-day intervals
Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Do a test of the inlet pressures
Examine the gas regulators
Examine the shield water regulator (if applicable)
Examine the air filter
Examine the connections between system components
Examine the coolant condition and level
Examine the water tube and torch
Examine the consumable parts
Examine the torch receptacle
Examine the torch lead
Table 2. Tasks for one-week, one-month, and six-month intervals
Task Week beginning: Week beginning: Week beginning: Week beginning:
Do a gas leak test
Do the weekly coolant check (coolant flow measurements)
Month (circle one) January February March April May June July August September October November December
Clean the internal surfaces of the system components
Examine the contactors
Examine the relays
Examine the gas line connections for leaks
Examine the ground connections
Examine the table-to-workpiece connection
Every 6 months - do coolant-system maintenance – Date completed: